Mazars

Mazars

MAIN CONTRACTOR: All Systems Commercial Fitouts
Value: €1,725,000.00
Client:  Mazars
Size: 35,000 square feet

 

Summary of Project:

All Systems completed a 40-week phased live refurbishment of Block 3, The Harcourt Centre, Harcourt Road, Dublin 2 for Mazars.  Works were spread over 7 floors

The main items of work involved the relocation of the reception and meeting suites from the Ground floor to the 6 th floor and the refurbishment and extension of all the office and open plan spaces to include a full Mechanical and Electrical upgrade.  We also installed a shower block at carpark level and a large staff canteen at Ground floor level.

DESIGN & PM: The Building Consultancy

PROGRAMME: 30 weeks

Scope of Works:

  • Removal of existing suspended ceilings, partitions, furniture and finishes
  • Construction of new solid and glazed partitions including decoration to form new breakout areas/meeting rooms & offices.
  • Installation of suspended ceiling.
  • Installation of new floor and wall finishes.
  • Installation of new manifestations.
  • Alterations/extension of the mechanical and electrical installations.
  • Installation of new tea stations and canteen.
  • Installation of new Basement level shower block.
  • Supply and fit of bespoke joinery units and timber baffles.